Business Paper Late Reports Demerger Transition Committee Meeting
Alby Schultz meeting Centre, Cootamundra
10am, Wednesday 15th April, 2026
Administration Centres: 1300 459 689 |
|
Demerger Transition Committee Meeting Agenda |
15 April 2026 |
LATE REPORTS
5.1.4 Update on Financial Sustainability Tender Schedule
|
15 April 2026 |
|
DOCUMENT NUMBER |
467915 |
|||
|
REPORTING OFFICER |
Peter Bascomb, Demerger Transition Manager |
|||
|
AUTHORISING OFFICER |
Roger Bailey, Interim General Manager |
|||
|
RELEVANCE TO COMMUNITY STRATEGIC PLAN |
|
|||
|
FINANCIAL IMPLICATIONS |
There are no financial implications associated with this report. |
|||
|
LEGISLATIVE IMPLICATIONS |
There are no Legislative implications associated with this report. |
|||
|
POLICY IMPLICATIONS |
There are no Policy implications associated with this report. |
|||
|
1. FSP Specification ⇩ |
|
That the committee endorses the changed schedule for the appointment of contractors to undertake the review and update of the Financial Sustainability Plan. |
Introduction
It has not been possible to meet the endorsed time frame for the advertising the tender for the update and review of the Financial Sustainability Plan. This report proposes a new time frame.
Discussion
The endorsed specification Financial Sustainability Plan specification (attached) included a proposed schedule that included the target of advertising the tender on 25 March 2026.
|
Date |
Milestone |
|
10 March 2026 |
DTC to consider FSP documentation and whether to recommend to Council. |
|
24 March 2026 |
Council to consider DTC’s recommendation |
|
16 April 2026 |
RfT released via Council’s usual channels |
|
15 May 2026 |
RfT closes |
|
9 June 2026 |
DTC considers RfT responses and selects successful contractor |
|
24 & 25 June 2026 |
Consultant induction |
|
8 September 2026 |
Preliminary findings presented to DTC |
|
13 October 2026 |
Draft FSP, LTFPs & revenue policies presented to DTC |
|
10 November 2026 |
Final FSP, LTFPs & revenue policies presented to DTC |
Financial
There are no additional costs because of the change to the timetable.
OLG 23a Guideline consideration
N/a